KPA Road Expansion Project Nears Halfway Mark as Port Infrastructure Upgrade Advances

By Katiwa Maneeno

MOMBASA, July 8 – The Kenya Ports Authority (KPA) has announced that the widening of Port Road from Gantry Workshop to Gate 18/20 has reached 49.3 percent completion, marking significant progress in one of the largest transport infrastructure projects within the Port of Mombasa.



The KSh8.344 billion project is designed to ease congestion, improve cargo movement and enhance operational efficiency by creating a modern grade-separated transport interchange linking the port with Kipevu Road and the Northern Corridor.

According to KPA, the project goes beyond a conventional road expansion and includes the construction of a 1.7-kilometre dual carriageway, with about 700 metres of elevated viaduct, reinforced concrete box girders, roundabouts, slip roads and access ramps to improve traffic flow for heavy port vehicles.


One of the project's most complex components is the excavation of Kipevu Hill, involving approximately 450,000 cubic metres of rock cutting and 150,000 cubic metres of engineered fill. A 265-metre Geosynthetic Mechanically Stabilized Earth (GMSE) retaining wall is also being built to protect nearby Kenya Pipeline Company petroleum storage facilities.

The project further includes relocation of critical infrastructure such as high-voltage power lines, water mains, fibre optic communication networks, stormwater drainage systems and the port's Integrated Security System to ensure uninterrupted operations during and after construction.

KPA said the contract was awarded through an open international competitive tender to a joint venture between Stecol Corporation and Miliki Development Company at a cost of KSh8.344 billion, with no variation to the contract since its award.

Works completed and ongoing include bored piling, pile caps, retaining walls, utility relocation, drainage structures, traffic management facilities and the commencement of the elevated viaduct superstructure.

The authority says the project remains on schedule and, once completed, will significantly improve cargo evacuation, road safety and the long-term competitiveness of the Port of Mombasa, while supporting growing trade volumes through Kenya's busiest seaport.

@Peopleandlifepaper

Comments

Popular posts from this blog

Pwani patriotic Religious Leaders Welcome Reduced School Hours, Urge Enforcement

Transport Paralysed as Nationwide Matatu Strike Hits the country.

Kenyan Chaplains Support New Curriculum